PowerPoint Presentation
Showing posts with label COVID-19. Show all posts
Showing posts with label COVID-19. Show all posts
Thursday, July 16, 2020
Friday, May 29, 2020
Construction Delays and COVID-19: Now is the Time to Review your Contract
The impact of the COVID-19 pandemic
on construction projects largely depends on the terms of the contract in play.
Now is the time to pull out your contract and consider how the contract
allocates risk for delays between the parties. While standard contract forms
are widely used in the industry, standard terms and conditions are frequently
modified as a result of negotiations between the parties. Provisions that
address project changes, force majeure, delays, and suspension of work should
be carefully reviewed by you and your counsel to determine how your rights or
responsibilities are impacted by COVID-19. Given the likely ongoing delays
faced by the construction industry, it is important that parties understand the
terms of their contracts to help curtail the economic impact of COVID-19.
Given the likely ongoing delays
faced by the construction industry, it is important that parties understand the
terms of their contracts to help curtail the economic impact of COVID-19.
An important provision to review,
if one exists, is the force majeure provision.1 A force majeure event, commonly
referred to as an “Act of God,” is one that is outside the control of a party
and prevents the party from performing its contractual obligations. While many
contracts include force majeure provisions, the specific language and the applicability
to particular events or circumstances, such as a pandemic, can vary. Many force
majeure provisions detail the timing and content of the required notice to
invoke such provision and allow for varying degrees of relief. Some contracts
that do not have a specific force majeure clause may contain an excusable delay
clause that may limit relief for such delays to an extension of time.
There may be circumstances where
the delays are intentional, and thus not excusable. An inexcusable delay occurs
when a party is at fault for the delay due to a party’s own fault or neglect.
For example, even though a contractor may be legally able to resume
construction activities, he may refuse to resume operations for other reasons,
such as health concerns related to COVID-19. Many construction contracts
contain provisions that allow for damages in the event of such non-excusable
delays. Conversely, some contracts may have a “no damages for delay” clause
that shields a party from liability caused by delays. Liability for delays will
depend on the specifics of the clause and the other terms in the parties’
contract.
Most contract provisions regarding
delays provide for specific notice requirements. When a contractor puts an
owner on notice of potential delays or other impacts, it is important to
carefully assess what it is that the contractor is asserting and requesting.
Some contractors are putting owners on notice of potential delays or other
impacts without any evidence purely to reserve their rights under the contract.
Others are requesting significant relief under the contract because they have
already experienced unexpected costs and delays. Therefore, the owner must
determine what the contractor or supplier is asserting before responding to any
notice.
It is important that parties
understand the terms of their contracts to help curtail the economic impact of
COVID-19. Whether a court will excuse a party from meeting its obligations
under a contract where performance becomes much more difficult or expensive as
a result of the COVID-19 pandemic remains to be seen. Based upon existing law,
judges and arbitrators will still most likely look to the terms of the contract
for guidance in resolving COVID-19 related claims.
Originally posted May 27, 2020 on
tlawmtm.com.
Wednesday, May 13, 2020
Guidance for Project Applicants and Conservation Commissions Conducting Meetings and Hearings, and Deciding Wetland Matters, During COVID-19 Crisis
The
Massachusetts Legislature has enacted a legal framework for municipal boards,
including conservation commissions, to receive
and process applications, conduct
meetings and hearings, make and issue decisions, take enforcement actions, and
otherwise function during the state of emergency declared by Governor Baker on
March 10th.[1]
This
is important to everyone with business of any nature before local, regional and
state agencies, not just projects and permits, but also contracts, transactions
and other public and private matters.
The
legislation is Chapter 53 of the Acts of 2020, known as “An Act to Address
Challenges Faced by Municipalities and State Authorities Resulting from
Covid-19” (the “Act”). It is intended to
function in harmony with Governor Baker’s March 12, 2020 “Order Suspending
Certain Provisions of the Open Meeting Law, G.L.
c. 30A, § 20”.
Section
17 of the Act tolls (legalese for pauses) many of the timelines which would
typically govern a commission’s hearing and decision process. It generally provides that the “clock” for
calculating such timelines stopped on March 10, and will resume 45 days after
Governor Baker declares the state of emergency to be over. So, the clock is
stopped, to resume later.
Let’s
see how this affects, for instance, conservation commission business. The state Wetlands Protection Act (“WPA”)
requires that a hearing be opened within 21 days of receipt of a completed
application, known as the Notice of Intent.
The
Act relieves commissions of this obligation by providing that it “is suspended
as of March 10, 2020” and “shall resume 45 days after the termination of the
state of emergency, or by a date otherwise prescribed by law, whichever is
later”. Section 17(b)(2).
As
an illustration, if a Notice of Intent were filed on March 15, the 21-day deadline
in the WPA for the commission to open the hearing would not begin until 45 days
after the state of emergency ends (that is, the hearing must open within 66
days after the state of emergency is terminated).
The
Act provides similar but not identical relief to commissions for hearings that
had already begun before or on March 10.
Section 17(b)(vii) specifically says that:
a hearing on a pending application for a
permit opened by a permit granting authority prior to March 10, 2020, which has
either not been concluded as of March 10, 2020 or has been continued by the
permit granting authority as of March 10, 2020, shall be automatically tolled
and continued to the first hearing date of the permit granting authority
following the termination of the state of emergency, or to a date otherwise
prescribed by law, whichever is later; provided, however, that the date is no
later than 45 days from of [sic] the termination of the state of emergency or
the date otherwise prescribed by law, whichever is later.
In
other words, if a hearing were opened and continued prior to or on March 10, it
is paused by the new Act until the commission’s first meeting date after
the state of emergency ends, so long as that date is not more than 45 days
after the state of emergency is over.
This automatic continuation requires no action by the commission.
By
giving the commission longer to open a new hearing than to decide under a
hearing already started, the Act essentially gives priority to projects which were
already in the pipeline when the Governor issued his Emergency Order on March
10, over those filed after the Emergency Order went into effect.
While
these automatic extensions of time and continuances of hearings are very
important, it is equally important to note that the Act provides a framework
for those commissions wishing to conduct business during the state of emergency.
It explicitly allows commissions to hold
remote/virtual meetings and hearings, and issue decisions, with some leniency
on compliance with the Open Meeting Law.[2]
We
encourage local boards to use this legal authority continue with as much pending
and new business as they are equipped and comfortable to handle under the
circumstances. It is important to keep things moving along where possible and
practical for all sorts of reasons. There is a new reason: to avoid a mammoth
amount of work when the present emergency is lifted and suddenly all the meetings
and hearings must be resumed and concluded, and all the backed-up decisions
made and issued, within a relatively short time.
Specifically,
Section 17(d) provides that a commission “during the state of emergency, may
conduct meetings and public hearings remotely, consistent with the governor’s
order entitled ‘Order Suspending Certain Provisions of the Open Meeting Law,
G.L. c. 30A, § 20’.” All other
provisions of the Open Meeting Law and its regulations remain in effect.
Section
17(c) of the Act also allows commissions to amend or revoke permits previously
issued “subject to applicable notice and hearing requirements”, with
limitations to protect applicants who have not begun, or have suspended, work
due to the state of emergency.[3]
If
a commission does decide to conduct some scheduling during the state of
emergency, it may do so without needing to hear and decided all matters pending
before it as of March 10, 2020. Section
17(b)(v) of the Act provides that:
notwithstanding
the time periods by which a permit is to be either heard or acted upon, a
permit granting authority may, by a declaration of its chair, which the chair
is authorized to make irrespective of whether a quorum is present to vote on
such matter, schedule or reschedule on 1 or more occasions the hearing or
decision deadlines on a permit application provided no such date or deadline is
rescheduled for more than 45 days after the termination of the state of
emergency or after a date otherwise prescribed by law, whichever is later. The
chair shall provide written notice of any applicable rescheduled dates or
deadlines to the applicant at the applicant’s address, and to the general
public by posting electronically on the website of the city or town clerk or
the website of the county or regional entity.
In
other words, a commission’s Chair is empowered to unilaterally (that is, with
or without a quorum present) continue, schedule, or reschedule a hearing or
deadline for decision on particular matters.
Note
the process to use this authority: the new date or deadline may not be more
than 45 days after the state of emergency ends; the Chair must give written
notice to the applicant by mail; and the Chair must notify the public by
posting notice electronically on the city clerk or town clerk’s website (or,
for regional or county commissions, on the regional or county website, where
applicable).
Finally,
the Act specifically allows a commission to issue a decision on a pending
application. Section 17(e) states that “[n]othing
in this section shall preclude or prohibit a permit granting authority from
issuing decisions on permit applications for which duly held public hearings or
meetings have been held.”
In
summary, the Act allows a conservation commission to effectively cease its
deliberations and decision making without violating the laws or risking appeals
for inaction, first by suspending the obligation to open hearings for
applications until 45 days after the termination of the state of
emergency.
For
hearings that were opened and continued prior to March 10, the Act automatically
tolls resumption of the hearing until the commission’s first meeting date after
the state of emergency ends (so long as that date is not more than 45 days
after the state of emergency is over) even with no action by the conservation
commission.
The
Act also allows commissions to hold remote/virtual meetings and hearings, and
issue decisions, while empowering the Chair to unilaterally continue, schedule
or reschedule a hearing or deadline for decision on particular matters not more
than 45 days after the state of emergency ends (so long as the Chair mails
written notice to the applicant, and posts notice electronically).
Stay
tuned for more legal developments on this front as there is more municipal and
state agency relief legislation, gubernatorial executive orders, court orders,
and agency regulations and guidance.
Luke Legere, Esq,
is a member of REBA, active with its Environmental Law Section, and a partner
at McGregor
& Legere, PC, in Boston, where he handles environmental,
land use, energy, real estate, and related permitting, transactions,
enforcement, appeals, and litigation for industrial, commercial, governmental,
non-profit, and individual clients. Luke
can be contacted at llegere@mcgregorlaw.com.
[1] This article
addresses only the conduct of meetings and hearings under state law, although
the Act addresses additional matters of importance to commissions.
[2] The Act also
suspends the requirement for recording a commission’s decision at the Registry
of Deeds or Land Court while they are closed or prohibit in-person access by
the public during the state of emergency. Section
17(b)(vi).
[3] Section 17(c)
also provides that “a permit holder shall be entitled to a further extension of
reasonable length to exercise or otherwise commence work” under permit “at the
discretion of the [commission] for good cause shown” and empowers the
commission’s Chair to “grant such further extension irrespective of whether a
quorum is present to vote on the matter.”
Subscribe to:
Posts (Atom)