When the unit owners of a
condominium take control of the condominium board of trustees, one of the first
tasks that the new board should undertake is to
investigate whether any
construction defects exist in the condominium common areas. Examples of such
defects may include water infiltration around windows or balconies, storm water
drainage issues, failure to meet building code requirements, and other
construction problems that should be corrected. The board’s investigation
typically involves hiring a licensed engineer to perform an inspection of the
common area and make findings about the conditions, including whether any
construction defects exist. When construction defects are found, the board will
often make a claim against the condominium developer seeking to recover the
costs to correct the defects. If the developer refuses to pay, the board will
have to consider whether to file a lawsuit.
A potential trap for the unwary
includes the time limits for construction defects claims that are imposed by
the applicable Massachusetts statutes.
A potential trap for the unwary
includes the time limits for construction defects claims that are imposed by
the applicable Massachusetts statutes. Generally speaking, under G.L. c.260, such claims are
limited to three years after the claim “accrues.” Under the “discovery rule,”
the claim accrues when the plaintiff knows or reasonably should have known that
the defect exists. If a condominium board learns of a defect in a common area
but waits more than three years to file a complaint in court, the lawsuit will
could be dismissed as time-barred under the statute of limitations. However,
there is a cut-off point at which any construction defects claim, no matter
when discovered, will be time-barred. Under what is called the “statute of repose”
(G.L. c. 260, § 2B), no claim
may be filed in court after six years have elapsed from the earlier of: “(1)
the opening of the improvement to use; or (2) substantial completion of the
improvement and the taking of possession for occupancy by the owner.” A court
may find that the statute of repose is triggered even during the period that
the condominium developer is in control of the condominium trust. Therefore,
when the unit owners take control of the condominium trust, the new board must
act quickly to determine whether defects exist in any common area to avoid the
potential pitfall of the statutes of limitation and repose.
A recent court decision by
Massachusetts Supreme Judicial Court emphasizes the importance of acting with
urgency in construction defects cases. In Bridgwood v. A.J. Wood Construction, Inc.,
issued last August, the Court considered a claim brought by a homeowner against
a contractor for construction defects. The homeowner, Bridgwood, argued that
his claim was not barred by the six-year statute of repose because it was not
merely a claim for negligence—rather, it was a claim for violation of the Massachusetts
Consumer Protection Act, G. L. c.93A (“Chapter 93A”).1
The Court disagreed and concluded that a claim under Chapter 93A for
construction defects is in effect the same as a negligence claim and therefore
subject to the statute of repose. Accordingly, the Court affirmed the trial
court’s dismissal of Bridgwood’s lawsuit for being time-barred under the
statute of repose because it was filed more than six years after the claim
accrued. The Court explained that the purpose of the statute of repose is to “protect
contractors from claims arising long after the completion of their work” and
will be enforced “despite the hardship [it] may impose on plaintiffs.”
The Bridgwood decision is notable in that it is a split decision, with
four justices voting in favor of affirming the dismissal of the plaintiff’s
case, and three justices voting against it. In a thoughtful dissenting opinion
written by Chief Justice Gants, the dissenters opined that no provision of
Chapter 93A suggests that the Massachusetts Legislature intended claims under
its provisions to be limited by the statute of repose. Judge Gants asked, “Why
would the Legislature seek to protect those who engaged in such unfair and
deceptive acts from [Chapter] 93A actions brought within the statute of limitations
by granting them a statute of repose that could potentially shield such
violations from any private cause of action by injured consumers?”
In a footnote to the Bridgwood decision, the majority opinion
invites the Massachusetts Legislature to amend the statute of repose to exclude
construction defects claims brought under Chapter 93A, if that is what the
Legislature actually intended. It will be interesting to see if the Legislature
reacts to the decision by amending the statute of repose. For now, the majority
opinion in the Bridgwood decision is
the law, and claims under Chapter 93A that involve construction defects are
subject to the six-year statute of repose.
The above-referenced case is
captioned Terry Bridgwood v. A.J. Wood
Construction, Inc., et al., SJC-12352 (Mass. SJC, August 29, 2018).