In the
case of Grand Manor Condominium Association v. City
of Lowell, the Supreme
Judicial Court established with clarity an important rule as to when the
statute of limitations begins to run for
filing in court a claim for property
damage under the Massachusetts Superfund statute, General
.Laws, Chapter. 21E, Section 5(a) (iii).
The SJC ruled that a claim for such damage due to contamination does not
accrue until the plaintiff learns that the damage is not reasonably or feasibly
curable.
Significantly,
the SJC said that this relatively late date for the deadline to begin to run ordinarily
is not until the environmental remediation process under Chapter 21E and the
Massachusetts Contingency Plan (“MCP”) is well advanced. The SJC rejected arguments that this claim
accrues at the relatively early date when the plaintiff first knew that there was
contamination.
In Grand Manor, the City had acquired in
1906 the property upon which the condominium was later built. In the early part
of the twentieth century it used the property as a quarry for mining rock and
gravel. During the 1940s and 1950s, it
used the site as a landfill. The
landfill was eventually covered and in 1983 the City conveyed the land to a
developer, who built the condominium.
A long
history of industrial use of a property over a period of many decades or longer
is a common feature of Chapter 21E cases.
In
November 2008, the condominium hired a contractor to install a drainage
system. The excavation quickly uncovered
solid waste and hazardous material. A
consultant was hired who began efforts to remediate it. In June 2011, a consultant’s report concluded
that there were 1.5 million cubic feet of hazardous material extending down to
bedrock. Restoring the site would cost approximately $11.7 million and was not
feasible.
Plaintiffs
filed suit on October of 2012 seeking
recovery under Chapter 21E, Section 4A for reimbursement of their response
costs and under Section 5(a) (iii) for the damage to their property. The statute of limitations for a claim under Section
5 is three years, as provided in Section 11A.
At
trial, the Superior Court ruled that the plaintiffs had the burden of proving
that their claim under Section 5 was timely and submitted the issue to the
jury, together with a list of several potential dates that could have triggered
the limitations period, including dates of preliminary work by the consultants
and the date of a demand letter by the plaintiff.
The
jury found that the plaintiff was entitled to reimbursement of response costs
under Section 4A but had failed to bring their property damage claim under Section
5 within the limitations period, and that claim was dismissed. This result was
appealed.
The
SJC considered the statute of limitations in the context of the over-all
statutory scheme and the regulations set forth in the Superfund law and MCP. The statutory and regulatory scheme sets out
separate phases of assessment and remediation, which eventually leads to a
decision about the appropriate level of cleanup, beyond which further cleanup
would be cost-prohibitive.
The
SJC said that full remediation of the contamination is desirable and, if that
occurs, the plaintiff has no cause of action under Section 5. It also said,
however, that the Superfund law and MCP do not require remediation of all
contamination in all cases, since that may not be financially feasible. It held that Section 5 provides for the
recovery of residual damage in that the property, even after undergoing the
mandated cleanup, still may contain pollutants that may diminish the fair
market value of the property. It said
that the plaintiff also may have suffered temporary loss of use that cannot be
cured or compensated by remediation and reimbursement of response costs.
The SJC
held that a plaintiff has suffered damage within the meaning of Section 5 if he
has suffered damage that is not reasonably curable through the clean-up process.
The cause of action under section 5 is triggered when he has knowledge that it
is not reasonably curable. “Such
knowledge is generally not provided until the MCP process is sufficiently
advanced.”
The SJC
said it would make little sense to hold otherwise. If the plaintiff were required to file suit
earlier, he might be required to file suit before he knows whether the
contamination can be reasonably remedied, that is, before he knows whether he
has a claim.
The SJC
vacated the judgment and remanded the case to the Superior Court. This likely
is for trial if the case is not settled.
Mike O’Neill is an associate at McGregor
& Leger P.C. He has more than 20
years of experience in real estate and litigation, including environmental law,
land use and commercial litigation, and conveyancing. Mike’s email address is moneill@mcgregorlaw.com.